Butwal
Power Company Limited (BPC) was established
in 1966 as a private utility to supply electricity
to a newly industrializing town in Western Nepal.
At present, the Company owns and operates two
hydropower plants with a total capacity of 17
MW and supplies electricity to about 21,000
predominantly rural consumers in Western Nepal.
It supplies the excess energy to the national
utility, Nepal Electricity Authority (NEA).
Since
its establishment, BPC’s mission has been
to generate and distribute electricity in the
most effective and efficient manner. BPC quickly
realized that distributing electricity in the
rural hills of Nepal was very different from
supplying electricity to urban areas. High cost
of the distribution network to cater to dispersed
and small loads was economically unviable. This
challenge will be discussed further in the next
chapter.
In
the late 1980s, BPC built the 5.1 MW Andhi Khola
Hydropower Project in Syangja District. As a
part of this project, BPC also undertook to
develop appropriate technologies as well as
suitable methods and tariffs for rural electrification
in the districts close to the power plant. This
initiated the development and uses of various
innovations in rural electrification that is
the subject of this paper. The ultimate aim
was to “establish a replicable model for
equitable and sustainable rural electrification”.
The
first phase of the rural electrification activities
in the Andhi Khola Hydel and Rural Electrification
Project (AHREP) was funded through grant assistance
from the Norwegian Government. Based on the
success during this phase, BPC received a grant
from the United States Agency for International
Development (USAID) in 1995 for rural electrification
expansion in the area. In addition BPC has invested
its own resources. Each year, BPC allocates
a percentage of its operational surplus for
rural electrification.
Source |
Amount |
Percentage |
|
NRs |
US$* |
|
BPC |
137,814,000 |
2,297,000 |
68% |
USAID
Grant |
34,722,00 |
579,000 |
17% |
NORAD
Grant |
31,583,000 |
526,0000 |
15% |
TOTAL |
204,119,000 |
3,402,000 |
100% |
A
breakdown of the total investment made by BPC
in rural electrification during the last 10
years is as follows.
| 2.
CHALLENGES OF RURAL ELECTRIFICATION IN NEPAL |
Electricity
is widely considered as an important ingredient
for socio-economic development. In the rural
hilly areas of Nepal, fuel wood is the major
source of energy. These areas have experienced
widespread deforestation, which has led to environmental
problems of soil erosion and drying up of water
springs. The inhabitants have very little disposable
income. Furthermore, the terrain is rugged and
houses are widely dispersed. Bringing electricity
to these villages poses Herculean challenges
in terms of effort and financial resources.
Furthermore, just bringing electricity poles
and lines to a village does not automatically
result in the economic revolution that a lot
of us imagine it would. Putting electricity
within the economic reach of the population
and promoting productive end-uses of electricity
is as challenging. BPC’s innovations in
rural electrification aim to address some of
these issues.
| 3.
INNOVATIONS IN RURAL ELECTRIFICATION |
A
number of technological and managerial innovations
were tried out at AHREP. In this paper, four
of the major innovations will be highlighted.
The two major technological innovations were
the intermediate 1 kV distribution voltage and
demand based tariffs. The two major managerial
innovations were the Electricity Users’
Organization and Motivators.
3.1
Technological Innovations – Distribution
Voltage of 1 kV
In
urban areas, electricity is distributed at either
400 V or 11 kV. Beyond about a kilometer range,
400 V lines have excessive voltage drop. 11
kV lines present practical problems to supply
the low but highly dispersed loads in the rugged
hilly rural terrain. Keeping this in mind, a
1 kV system was used where many line accessories
for 400 V lines were used. This extended the
service distance from about 1 km to about 5
km. Furthermore, a 1 kV system discouraged theft
of electricity because tapping these lines did
not give consumers a usable voltage. However,
one of the most significant advantages of the
1 kV system was that 1/0.23 kV, 1 kVA and 2
kVA transformers were relatively inexpensive
and light enough to be carried by porters into
even remote service areas. In comparison, even
the smallest 11 kV transformers are quite heavy
and small sized transformers in this voltage
are comparatively expensive.
3.2
Use of Demand Based Tariff
In
rural areas in Nepal, the electricity consumption
is very low. Therefore, using an energy based
tariff structure does not yield high revenue.
On the other hand, the operational costs associated
with meters, meter reading, account keeping
and collecting are high, and may at times be
higher than the revenue generated. A tariff
structure based on subscribed demand (power)
does away with meter reading and the associated
complicated tasks of account keeping. Furthermore,
in rural areas, strictly limiting demand is
essential for reducing the cost of distribution
lines. Furthermore, if the distribution is from
a run-of-river plant without an access to the
grid (as in micro-hydro applications), power
is more valuable than energy.
3.3
Managerial Innovations
Electricity
Users’ Organizations (UOs). As mentioned
above, building rural electrification networks
is expensive. Operating these networks is also
very labor intensive. Carrying out simple routine
maintenance and collecting dues, which are simple
matters in urban and roadside settlements, present
difficulties for remote and dispersed locations.
Technicians have to travel for hours to carry
out a simple task that can be completed in minutes.
Collecting dues from farmers who are often away
from home in their fields during the day may
take many days’ work for an outsider.
The UOs, established by BPC, mobilize local
resources for construction of lines in the form
of labor and local materials. During maintenance,
these UOs carry out simple maintenance of the
system and collect dues and deposit them in
the company offices. For their contribution
to the operation of the network, 10% of the
fees collected are refunded to the UO. The UO
uses this fund to pay a serviceman to carry
out the tasks. In addition to reducing the cost
of constructing and operating the network, the
UOs help channelize the social capital in the
villages and instill a sense of ownership the
distribution system among the consumers.
Motivators.
Motivators are local youths who have been trained
to familiarize rural consumers with various
aspects of electrification such as safety, end
use promotion, tariff etc. In many villages,
there are people who have never experienced
electric lighting before, let alone other uses
of electricity. Concepts and devices we take
for granted are novelties for many in rural
areas. Therefore, consumers have to be educated
about productive uses of electricity, the relevant
tariff rates, safety, connection procedures
etc. Local youths, preferably local married
couple, are hired so that the locals feel free
to talk to someone from their neighborhood,
and share their own ideas, feelings and frustrations,
rather than listening passively to some outside
expert. Various methods like drama, presentations,
house visits, demonstrations are used as motivation
tools.
| 4.
BPC’S RURAL ELECTRIFICATION EFFORTS |
At
present BPC has 20,766 consumers. The breakdown
of the consumers is as follows.
Concumer
Category |
Number
of Consumers |
Metered |
5,227 |
Cutout
(Demand based) |
15,319 |
Industrial |
220 |
TOTAL |
20,766 |
The
total number of consumers served by 1 kV system
is 12,668. There is a total of about 277 km
of 1 kV lines. Distribution transformers of
100, 200 or 250 kVA step down the voltage from
33 kV to 1 kV. 1 kV lines are then taken to
load centers, which may be anything from a small
sized bazaar to a cluster of a few houses. Then
single-phase transformers of 1 or 2 kVA, or
three phase transformers of 5, 10 or 25 kVA
further step down the voltage to 230 V. The
details of the transformers are given below.
Transformer
Specification |
Number
|
33/1
kV, 100 kVA |
8 |
33/1
kV, 200 kVA |
3 |
33/1
kV, 250 kVA |
2 |
1/0.23
kV, 1 kVA |
148 |
Transformer
Specification |
Number
|
1/0.23
kV, 2 kVA |
167 |
1/0.4
kV, 5 kVA |
38 |
1/0.4
kV, 10 kVA |
76 |
1/0.4
kV, 25 kVA |
43 |
The
cutout consumers subscribe for demands from
25 watts to 400 watts. The breakdown of the
cutout consumers is as follows.
Watts |
Number
of Consumers |
25 |
125 |
50 |
1,454 |
100 |
6,605 |
250 |
6,057 |
400 |
1,053
|
800 |
18 |
TOTAL |
15,319 |
A total of 11,881 consumers are served through
55 UOs in the BPC distribution system. The average
size of a UO is 216 households (consumers).
However sizes range from 36 to 380 consumers.
There are typically 3 to 6 UOs supplied from
a distribution transformer.
| 5.
EXPERIENCES WITH THE INNOVATIONS |
5.1
Distribution Voltage of 1 kV
The
1 kV lines usually consist of ACSR conductors
strung on tubular steel or wooden poles using
porcelain shackle insulators used in 400 V lines.
However, self-supporting insulated aluminum
cables have also been used. These lines emanate
at the 33/1 kV distribution transformer and
end in the 1/0.23 kV transformers at load centers.
The transformers were previously protected on
the 1 kV side using 400 V MCCBs, which are tested
for up to 1 kV voltage. However, they were prone
to frequent insulation failure both between
phases and to earth.
Nowadays,
either HRC or kit-kat fuses are used. A bigger
distance is maintained between phases, and fuses
are installed on a fiberglass plate to strengthen
the insulation to earth. As discussed above,
one of the advantages of the 1 kV system over
the 11 kV system is that the 1 kV transformers
can be built to small sizes. BPC uses 1, 2,
5, 10 and 25 kVA transformers depending on accessibility
and load size. These transformers are lightweight
and thus easy to transport. For a number of
years, these transformers were dry-type. However,
during the monsoon, they frequently failed because
of moisture and lightning strikes. Based on
this experience, most of these transformers
have now been immersed in oil by fitting an
outer tank. This has strengthened the insulation
of the transformer, resulting in a drastic reduction
in failure.
In many areas, there has been pressure to extend
the 1 kV lines beyond 5 km resulting in excessive
voltage drops. Furthermore, because of a massive
road building drive by local governments and
communities in the past few years, previously
inaccessible areas have become accessible. Consequently,
BPC is planning to convert some of the 1 kV
lines into 11 kV lines. However, this is not
a failure of the 1 kV system but rather a change
in the socio-geographical conditions in the
distribution area, brought about by increase
in population density and accessibility.
The
1 kV voltage system is still relevant where
the consumers are located in small groups and
are widely dispersed. It may specially be applicable
in remote areas served my micro hydro power
plants where 400 V lines result in excessive
voltage drop.
5.2
Demand Based Tariff
When
the tariff structure was introduced in the early
1990s, it was assumed that the power from the
5.1 MW Andhi Khola plant would be quickly used
up for rural electrification. At the time, there
did not exist a power purchase agreement (PPA)
with NEA. Consequently, it was assumed that
power rather than energy would be the major
constraint. However, a PPA has since been signed
with NEA, according to which all excess energy
from the plant is supplied to NEA. Even then,
the power or demand based tariff is relevant
in the rural distribution areas. Because of
the reduction in costs associated with metering,
it has been possible to provide electricity
to the lowest income group consumers at very
affordable rates. Over 50% of the cutout consumers
subscribe for less than 100 W. These are households
that use from one to four 25 W bulbs in their
houses. Thus, the demand-based tariff has been
very successful in making electricity available
to the consumers in the lowest income group.
The
major technical challenge has been to find a
reliable current controlling device for very
low current levels. Presently, positive thermal
coefficient devices (PTCs) are used for 25 and
50 W consumers, and German-made MCCBs for the
other categories.
5.3
Electricity Users’ Organization
The
three main advantages that BPC saw in forming
Users’ Organizations were:
 |
·
Reduction in cost of the distribution system
construction,
· Reduction in BPC’s burden
in administering the distribution system,
and
· Assistance in building social capital
in the community. |
BPC saw the UO as an informal community organization
that assists BPC in reducing the cost of rural
electrification. For the remote areas, BPC stipulated
that it would deal only with Uos and not individual
onsumers. Communities interested in being supplied
with electricity would have to organize themselves
into a UO. These UOs were entrusted with the
following tasks:
 |
·
Gathering and submitting applications to
BPC,
· Organizing local labor and local
materials contributions,
· Collecting fees from consumers
and depositing it with BPC,
· Assuming responsibility for simple
maintenance of the system within the UO
area, and
· Serving as a communication link
between the community and BPC. |
Typically,
BPC receives an application for electrifying
a village or a group of villages. BPC then conducts
a study of the area with respect to system design
and cost of the system. The findings of the
study and BPC’s condition for electrification
are presented to the community leaders. If the
community is still interested, they are asked
to organize themselves into a UO and select
members for the UO Executive Committee. During
construction, frequent meetings are held between
BPC and the UO, while BPC supplies technical
manpower and non-local materials. The UO has
to supply all unskilled labor and locally available
materials such as wooden poles, sand, pebbles
and stones etc. In the meantime, one or two
members of the UO are trained to serve as servicemen
during the operation phase. The training is
mostly on-the-job. The serviceman will later
be responsible for collection of dues and simple
maintenance and repairs within the UO area.
BPC also provides the UO with a small starting
capital for buying tools etc.
The
ownership of the system is always with BPC.
It has been BPC’s experience that there
are always more areas wanting electricity than
available funds would allow. Thus, BPC views
community contributions as a way to reduce construction
costs so that more areas could be electrified
with the available budget. In addition, community
contributions also allow more remote communities
to enable BPC to electrify their houses at the
BPC’s cost-per-consumer limit of NRs.
10 to 12 thousand (US$ 130 to 160). For the
work that the UO does for BPC during operation,
BPC refunds 10% of all fees and dues collected
by the UO. This is primarily used to pay the
salary to the serviceman.
BPC
has had about a decade of experience in implementing
the innovations described above. Though a rigorous
financial analysis about the savings achieved
thus far has not been carried out as of yet,
there is a consensus among BPC’s technical
staff that the results have been promising.
The
1 kV distribution system serves 61% of the consumers
through 215 km of lines and about 1.9 MVA of
transformer capacity. This system seems suitable
to distribute electricity up to about 5 km line
distance in remote hilly areas, areas typically
served by micro hydropower. The ease of transportation
of lightweight transformers is seen as one of
its main advantages.
The
consumers subscribing to a pure demand based
tariff constitutes 74% of the consumers. This
type of tariff has specially benefited consumers
with very low income. BPC is still experimenting
with different type of current cutout devices.
The success of this tariff rests on a reliable
cutout device. The advantage associated with
reduction in metering costs is clearly evident.
About
57% of the consumers are served by UOs. The
Uos in BPC’s distribution area has sown
the seed for community owned distribution systems,
a concept that is being aggressively promoted
by Nepal national utility, NEA.
BPC
intends to continue its study of these and other
innovations in rural electrification. BPC’s
vision is to aggressively expand its distribution
area in the next few years. Rural electrification
will continue to be a major BPC activity during
this expansion. With further refinement, BPC
hopes to prove that sustainability and equity
can be achieved in rural electrification. Many
of these innovations are relevant for distribution
of power by mini and micro hydro plants in remote
hilly areas as well as grid-connected community
owned systems. BPC aims to disseminate these
innovations to the concerned stakeholders, such
that benefits of the innovations can be experienced
in a much larger scale.
1.
Allen Inversin, “New Designs for Rural
Electrification – Private Sector Experiences
in Nepal”, NRECA, Washington, USA, 1994
2. Proposal submitted to USAID
for Funding of Andhi Khola Hydel and Rural Electrification
Project Phase II, BPC, Kathmandu, Nepal, 1995
3. BPC internal documents